Why the Walkway Hung From the Wrong Nuts

Chapters

About this video

The Hyatt Regency walkway collapse of 1981 remains the deadliest structural failure in U.S. history. This video explains the fatal connection change that doubled the load on the fourth-floor box beam, leading to a progressive collapse that killed 114 people. Chapters: 00:00 The Collapse 00:11 The collapse occurred under loads substantially 00:24 The change 00:36 The change order 00:47 Load on fourth-floor connection 01:02 The fatal connection 01:12 The flange gives way 01:25 The first connection fails 01:39 The scale of the disaster 01:50 The collapse occurred under loads substantially 02:11 The Original Rod Design 02:25 The Doubled Load 02:49 The Load Path 03:14 The Moment of Failure 03:25 The Redistribution 03:50 The Fourth Floor Falls 04:02 The Second Floor Collapses 04:35 The Investigation 04:50 The Code Loads 05:18 The Bearing Area 05:33 The First Crack 06:02 The Cascade Begins 06:16 The Falling Walkway 06:29 The collapse lasted only seconds 06:40 The Investigation's Focus 06:56 The Professional Reckoning Sources & further reading: • nist.gov — https://www.nist.gov/el/walkway-collapse-kansas-city-missouri-1981 • nvlpubs.nist.gov — https://nvlpubs.nist.gov/nistpubs/Legacy/BSS/nbsbuildingscience143.pdf • nist.gov — https://www.nist.gov/publications/investigation-kansas-city-hyatt-regency-walkways-collapse-nbs-bss-143 • firedoc.nist.gov — https://firedoc.nist.gov/article/t3cyXYQBWEcjUZEYe498 • nist.gov — https://www.nist.gov/publications/investigation-kansas-city-hyatt-regency-walkways-collapse • books.google.com — https://books.google.com/books/about/National_Bureau_of_Standards_Science_Ser.html?id=yAYM0AEACAAJ • archive.org — https://archive.org/details/investigationofk8224mars • id.scribd.com — https://id.scribd.com/document/245619839/Hyatt-Regency-Collapse-NASA-Article

From the video

The Collapse
The Collapse
Why the Walkway Hung From the Wrong Nuts
The Cause
The Cause
The collapse occurred under loads substantially less than the code design loads.
The collapse occurred under loads substantially less than the code design loads.
The original design
The original design
The change
The change
The revised detail made the fourth-floor box beam connections carry the load of both walkways.
The revised detail made the fourth-floor box beam connections carry the load of both walkways.
The change order
The change order
The revised detail made the fourth-floor box beam connections carry the load of both walkways.
The revised detail made the fourth-floor box beam connections carry the load of both walkways.
The overloaded connection
The overloaded connection
The trap set
The trap set
The fatal connection
The fatal connection

More from Load Path